Well, school is on holiday this week, but not the builders and the works on site continue to progress well. This week we have continued to focus on the following:
• Continue to construct the link road between the existing school carpark and the new project • Continue the gabion baskets to the school boundary
• Continue re-shaping all the ground to the rear of the school / new project • Completed the installation of the first phase of the precast concrete floor slabs • Works have started to the link corridor between the new project and the existing school • Works are now ready for the Structural Steelwork. This is due to start next Monday with another crane due on site !!