The works on site continue to progress well. It’s been very hot and everyone has been working really hard in the sun. This week we have continued to focus on the following: • The brickwork to the foundations has been finished • Continue to construct the link road between the existing school carpark and the new project • Continue the gabion baskets to the school boundary • Continue re-shaping all the ground to the rear of the school / new project • The crane finally arrived on Monday and we have started installing the pre-made concrete floor slabs to the building area. The first phase should be complete during next week, in readiness for the steelwork to commence