Well it’s been another busy week - sometimes sunny, sometimes wet - but the works on site continue to progress well. This week we have continued to focus on the following: • The brickwork to the foundations will be finished this week • The drainage inside the building is now finished and the ground underneath the ground floor has been levelled • Continue to construct the link road between the existing school carpark and the new project • Constructing the gabion baskets to the school boundary • Making a start re-shaping all the ground to the rear of the school / new project • Unfortunately, due to the weather we had earlier in the week, the cranes have not been able to get to site this week. However, they are due to be here at the beginning of next week (week 10) to start installing the pre-made concrete floor slabs