The works on site continue to progress well. This week we have continued to focus on the following: • Installing the Brickwork into the foundations to get them to the correct height • Installing the drainage pipework inside the new building • Digging the new road that connects the existing school to the new project • Getting things ready for when the cranes are due on site to start lifting in the pre-made floor slabs (which are due to start in Week No 9) • Removing all the topsoil to the area behind the school ready for re-shaping the ground